Latest BMS Insights
Expert insights and practical guidance for optimizing your building management systems
BMS Retrofit Case Study: 66 Goulburn, Sydney
Retrofitted a 15-year-old BMS with a modern, open-source Tridium Niagara head-end and BACnet hardware—delivering flexible, future-proof control. Delivered significant early energy reductions, with a 20% reduction in rolling 12-month consumption.
Read More →
Seamless BMS Integration Achieves PCA A-Grade and NABERS Goals at 320 Pitt Street
OzTech upgraded mid and high-rise BMS systems to PCA A-grade standards for a Federal Government tenancy. OzTech delivered energy-saving strategies targeting NABERS 5 stars while improving building performance, comfort, and efficiency with minimal maintenance disruption.
Read More →
$1M+ BMS & Network Retrofit at Premium Sydney CBD Retail Hub
OzTech delivered a full BMS retrofit and ICN infrastructure upgrade, seamlessly transitioning from legacy systems to open architecture. With strong stakeholder coordination and risk mitigation, our BMS service team installed over $1 million in hardware replacements, achieving more than 30% energy savings.
Read More →
Seamless BMS Integration for a Heritage Education Site
OzTech completed a complex BMS retrofit, replacing aging pneumatic hardware and incompatible DDC platforms. Our BMS projects team upgraded 20 air handling units, 60+ fan coil units, and 60 induction units within a strict two-week holiday window, achieving a 20% energy reduction through coordinated mechanical upgrades and seamless execution.
Read More →
42% Energy Savings from Two Weeks of Smart BMS Controls at 255 Pitt St, Sydney
OzTech delivered a high-impact energy upgrade that achieved a 42% reduction in chiller consumption, 20% lower year-to-date electricity use, and 127,400 kWh saved in just five months. With only a $10k initial investment, the project delivered rapid payback while also improving NABERS by +0.5 stars.
Read More →Threading the Needle: Police HQ’s High Stakes BMS Retrofit
OzTech successfully delivered one of our most complex BMS retrofit projects, migrating 431 VAV boxes, 96 air handling units, and 2 cooling towers from a fragile LonWorks-based legacy head end to a modern platform. Completed in stages with zero downtime, our BMS service team ensured no tenant disruption while meeting aggressive timelines.
Read More →77 Market Street Wollongong, BMS Retrofit and Service Takeover Success
Live migration from decades old proprietary legacy head end and hardware to a new head end in multiple stages with no major faults or service interruption.
Read More →From 3.5 to 5 Stars: A Five-Year NABERS Transformation at Citadel Towers
This BMS project delivered major energy and cost savings by installing a new BMS with predictive HVAC controls, upgrading to smart LED lighting, and replacing old chillers with high-efficiency Turbocor units.
Read More →