Project Snapshot

Project ElementDetails
ClientISPT
Project Address644 George Street, Sydney, NSW
Project TimelineThe project was completed in January 2021
Services ProvidedFull replacement of the legacy Schneider BMS with a Tridium Niagara N4 headend and EasyIO DDC controllers. Design and deployment of a new site-wide Information and Communications Network (ICN), including fibre and CAT6 cabling, CISCO Meraki core and access switches, and DELL server infrastructure. Supply, installation, testing, and commissioning of all network and system components.
PartnersISPT, Compass Intelle (BMS consultants), and Grosvenor Engineering Group (mechanical contractor).

Building Background

World Square Retail, located at 644 George Street, Sydney, NSW, is a premium commercial complex spanning over 16,500 square meters and hosting more than 150 retail outlets.

Owned by ISPT, the facility previously operated on a proprietary Schneider Electric LON BMS, which had reached end-of-life. The client sought a modern, open-architecture system that could offer better visibility into building operations, improve energy efficiency, and support long-term asset performance.

OzTech was engaged to perform a comprehensive system transformation.

  • Full replacement of the legacy Schneider BMS with a Tridium Niagara N4 headend and EasyIO DDC controllers.
  • Design and deployment of a new site-wide Information and Communications Network (ICN), including fibre and CAT6 cabling, CISCO Meraki core and access switches, and DELL server infrastructure.
  • Supply, installation, testing, and commissioning of all network and system components.
  • Coordination with ISPT, Compass Intelle (BMS consultants), and Grosvenor Engineering Group (mechanical contractor).

All work was delivered in a live retail environment with strict requirements for zero service disruptions.

The OzTech Difference

Technical Expertise

Leveraging deep knowledge of proprietary and open BMS protocols.

Risk Management

Methodical project delivery to mitigate operational risks in a live environment.

Integration Mastery

Seamless system cutover with no disruption to services.

Client Alignment

Working closely with all stakeholders to deliver a solution aligned with ISPT’s long-term goals.

Proven Outcomes

Achieved over 30% energy savings, validating system ROI and operational improvements.

Looking Ahead

OzTech continues to provide managed services for the site’s ICN infrastructure and is actively supporting ISPT in identifying further energy optimisation strategies.

  • Data insights are being leveraged to inform NABERS rating improvement plans and long-term asset performance enhancements.
  • OzTech remains a trusted partner ISPT’s BMS solutions, with key projects including our recent service takeover success at 255 Pitt Street.